GENERAL

1.                  INTRODUCTION

Pursuant to the clause 19.4(a) of the Haryana Transmission and Bulk supply license the licensee shall plan and operate its Transmission System and shall plan procurement of electricity and make the same available to Distribution Licensees in conformity with the following standards.

S.N

Standards

Chapter

a)

Transmission System Planning and Security Standards

1

b)

Power Supply Security Planning Standards

2

c)

Transmission Operating Standards

3

d)

Power Supply Operating Standards

4

Not withstanding anything contained in these standards the Licensee shall not infringe or violate any of the provisions of the Indian Electricity Rules 1956.

2.        DEFINITIONS

2.1         In these standards, unless the context otherwise requires

S.N

 

Definition

1

Act

Haryana Electricity reform Act 1997

2

Rules

Indian Electricity Rules, 1956

3

Grid Code

Code prepared by the Licensee in accordance with the terms of Condition -17 of the Transmission and Bulk Supply License, 1999. and approved by the Commission.

4

Grid Code Review Panel/Panel

a panel set up under Grid Code

5

Generator

an organisation that generates electricity and who is subject to the Grid Code

6

CBIP

Central Board of Irrigation and Power

7

CEA

Central Electricity Authority

8

HERC/Commission

Haryana Electricity Regulatory Commission

9

NREB

Northern Regional Electricity Board

10

NRLDC

Northern Regional Load Despatch Centre

11

PGCIL

Power Grid Corporation of India Ltd

12

Licensee

holder of the Haryana Transmission and Bulk supply License.

13

EHT

Extra High Tension

14

HT

High Tension

2.2         Words and expressions used but not defined in these standards and defined in the Electricity (Supply) Act, 1948 (Act No. 54 of 1948), have the meanings respectively assigned to them in that Act;

2.3     Words and expressions used but not defined either in these standards or in the Electricity (Supply) Act, 1948 (Act No. 54 of 1948) and defined in the Electricity (Supply) Act, 1948 (Act No. 54 of 1948) and defined in the Haryana Electricity Reforms Act, 1997 (Act No.10 of 1998) and defined in the Indian Electricity Act, 1910 (Act No. IX of 1910), have the meanings respectively assigned to them in that Act;

 